Hazards Green Pipeline – East Sussex

Project Info

  • Project Value

    £500,000

  • Category

    Water Treatment Works

Job Title

Hazards Green Pipeline

Client

South East Water

Description

The works comprised of the installation of approximately 4km of 450 diameter ductile iron pipeline between Hazards Green Water Treatment Works and Windmill Hill to replace the 9” cast iron main between Boreham Street and Windmill Hill, and the 10” cast iron main between Hazards Green Water Treatment Works and Boreham Street.

Additional reinforcement works were undertaken on a 450m, 300mm diameter pipe laid parallel to the existing ductile iron.

Duration

12 Weeks